Commercial solar and network connection in WA

A decision path for WA businesses assessing load, site constraints, network connection and the commercial basis of a solar project.

Maintained by
McKercher Corporation
Status
Published · reviewed
For
Customers, Industry, Partners
Review connection references
Maintained byMcKercher CorporationPublishedReviewed
For

Customers, Industry, Partners

Review connection references
00
Start here

Commercial solar should be scoped as an energy and connection project, not only an equipment purchase. Interval demand, operating hours, roof and switchboard constraints, network hosting capacity, export conditions and the status of any announced incentive all affect the viable design.

Decision framework

Checks before a decision is made

Work through the identity, evidence and delivery chain. One credential, component or headline figure does not establish that the complete proposal is suitable.

  1. 01
    Load

    Begin with interval demand

    Use recent interval data, operating hours, seasonal demand and planned loads to distinguish useful on-site generation from unmanaged export.

  2. 02
    Site

    Establish physical and electrical constraints

    Review roof condition and access, structural capacity, switchboards, metering, phases, fire and maintenance access, and the route to the point of connection.

  3. 03
    Connection

    Identify the network pathway early

    System size, export intent and site characteristics determine the information and technical review required by Western Power. Approval should not be assumed from array capacity alone.

  4. 04
    Status

    Separate current rules from announcements

    Treat the announced expansion of the Small-scale Renewable Energy Scheme as conditional until the final instrument and regulator guidance are operative.

  5. 05
    Case

    Model the commercial case transparently

    State tariff, load, generation, degradation, curtailment, maintenance, financing and certificate assumptions so the business case can be tested.

  6. 06
    Evidence

    Plan approvals and handover records

    Retain design inputs, connection correspondence, approvals, certificates, commissioning results and asset information for operations and future changes.

What to do next

The next step

Primary

Contact McKercher with recent interval demand data, site constraints and the expected system capacity under consideration.

Discuss a commercial energy requirement
Check directly

Check current connection, export and technical requirements directly on Western Power's guidance for solar installers before fixing a design.

Review Western Power's technical guidance (opens in a new tab)
01

Feasibility and project definition

Establish the interval load, site constraints, network pathway and assumption register before fixing system capacity.

02

Policy and connection settings

Track the announced certificate expansion and the WA work affecting larger distributed energy connections.

03

Business and delivery context

Review the organisational and infrastructure context behind sustained commercial energy delivery.

Continue the decision

Related checks that usually follow

Common questions

Points requiring an explicit answer

Does a certificate entitlement guarantee network approval?

No. Certificate eligibility and network connection are separate. Western Power assesses the proposed connection and may apply technical or export conditions.

Is the announced 1 MW small-scale scheme threshold already in force?

At review on 14 August 2026, it remained an announced change scheduled for 1 October 2026 and subject to regulation. Current law and Clean Energy Regulator guidance should be checked before it is used in a proposal.

Should a business size solar to available roof area?

Not by itself. Interval demand, network limits, operating hours, future electrification and the commercial assumptions should shape capacity before unused roof area is treated as the target.

When should the connection pathway be assessed?

Early in feasibility. A project can be technically sound behind the meter while facing export, data or approval constraints at the network connection.